|
![]() |
|
| http://ior.rml.co.uk | Published by the DTI Oil & Gas Directorate for the reservoir
engineering and IOR community in the UK. Send comments on this issue and contributions for next issue to iornewsletter@senergyltd.com by 30th April 2003. | |
| Click Here for the Main Articles Index |
CO2 Flooding of UKCS Reservoirs |
|
![]() Eugene Balbinski |
Eugene Balbinski (eugene.balbinski@ecltechnology.com) of ECL Technology Ltd (http://www.ecltechnology.com) summarises the findings of work undertaken for the DTI’s Oil and Gas Directorate under the SHARP programme investigating the potential for CO2 injection in UKCS reservoirs. The physical properties of CO2 make it a potentially significant
IOR (Incremental Oil Recovery) injection gas, with application in situations
that would not benefit from hydrocarbon gas injection. The history of
successful CO2 injection projects in the US Permian Basin bears
testimony to this view. CO2 injection could increase UKCS reserves
substantially and dispose of a significant fraction of the CO2
emitted by the Tertiary CO2 injection in onshore North American fields is a successful IOR technique that regularly achieves incremental oil recoveries in the range 4-12% STOIIP (Stock Tank Oil Initially In Place). Retained gas volumes are typically 10-25% HCPV (Hydrocarbon Pore Volume) for tertiary CO2 WAG (Water Alternating Gas) floods. The incremental oil production, expressed in reservoir barrels, is generally between 50 and 100% of the volume retained in the reservoir. Although UKCS fields are at higher pressures than onshore CO2 projects, the higher temperatures compensate to give similar CO2 densities at reservoir conditions in both UKCS and Permian Basin floods. Consequently, similar quantities of CO2 would be required to sweep a given reservoir volume in both cases. Benefits
The total volume of incremental oil available from CO2 injection into UKCS reservoirs has been estimated from historical screening work at roughly 1700 MMstb. Note that the data on which this work was based is mostly at least ten years old, though this should be adequate for a preliminary estimate. It can be seen from Figure 2 that peak incremental recovery rates in excess of 500 MMstb/d may be achievable in the period 2015 to 2020. The bulk of the initial incremental recovery is expected from a relatively large number of WAG projects, though the bulk of the total recovery is estimated to be provided by a few large GSGI (Gravity Stable Gas Injection) projects. Although this is likely to be generally correct, if the work on which these estimates were updated, it is probable that it would now be thought that WAG would be a more appropriate technique for some of the larger GSGI schemes. Figure 2 probably therefore underestimates the likely contribution from WAG schemes. This is important as these would be of shorter duration and potentially more economic, as incremental oil is achievable earlier in a project’s lifetime.
The total CO2 that might be sequestered by reservoir injection has been estimated from the same data to be about 700 million tonnes. This is about 1.4 times total estimated UKCS emissions for 1999. Figure 3 shows that the bulk of the sequesterable CO2 is from GSGI schemes. This conclusion is also subject to the same possibility that a greater share might be found to be due to WAG schemes if the work on which it is based were updated. However, it is more robust because GSGI schemes, if applicable, are intrinsically a more efficient way of sequestering gas than WAG schemes, as most of the gas injected can be sequestered. This is because the GSGI technique essentially relies on gradually filling the whole reservoir with gas, whereas WAG schemes may successively re-cycle gas, flooding different limited pathways through the reservoir each time. The degree of re-cycling necessary in WAG schemes is very dependent on particular field heterogeneities and therefore cannot be reliably estimated from the screening work on which these results are based. The volume of gas re-injected is therefore likely to be higher for WAG schemes, than for a good GSGI scheme.
It can be seen from Figure 4 that the window of opportunity for UKCS CO2 injection is limited. By 2005 the potential for incremental oil will start to decline significantly and will suffer a steep decline after 2011. Most of the potential at risk from delay initially is from WAG schemes, as these should be implemented a few years before production would otherwise cease. GSGI schemes may be left until a reservoir is close to ceasing production.
Development Scenarios
A key issue in developing any strategy is the phasing of the infrastructure development and the timing of CO2 injection in specific reservoirs, taking into account the window of opportunity provided by the remaining life of the target fields. The most appropriate strategy developed will depend on the effective cost of CO2. If CO2 has a price purely determined by the cost of separation and transport, then strategies will be favoured that maximise the volume of incremental oil recovered for the CO2 retained in the reservoir. For example, WAG floods could be followed with a further waterflood to recover mobile CO2. Alternatively, if there is an environmentally driven fiscal incentive for sequestering CO2, it may be attractive to run CO2 injection schemes sub-optimally in a classical IOR sense, to increase the volume of CO2 retained in reservoirs. |
|
| Disclaimer: |
Disclaimer: The material available on this website is designed to provide general information only. Whilst every effort has been made to ensure that the information provided is accurate, it does not constitute legal or other professional advice. |
|